34In addition, it must be stated that, in accordance with settled case-law, a national court which is called upon, within the exercise of its jurisdiction, to apply provisions of EU law, is under a duty to give full effect to those provisions, if necessary refusing of its own motion to apply any conflicting provision of national law, and it is not necessary for that court to request or to await the prior setting aside of that provision of national law by legislative or other constitutional means (see judgments of 20 October 2011, Interedil, C‑396/09, EU:C:2011:671, paragraph 38 and the case-law cited; of 4 June 2015, Kernkraftwerke Lippe-Ems, C‑5/14, EU:C:2015:354, paragraph 32 and the case-law cited, and of 5 April 2016, PFE, C‑689/13, EU:C:2016:199, paragraph 40 and the case-law cited).