40In the light of the foregoing, the answer to the question is that Article 2 of Directive 2004/18 must be interpreted as meaning that, following the award of a public contract, a material amendment cannot be made to that contract without a new tendering procedure being initiated even in the case where that amendment is, objectively, a type of settlement agreement, with both parties agreeing to mutual waivers, designed to bring an end to a dispute the outcome of which is uncertain, which arose from the difficulties encountered in the performance of that contract. The position would be different only if the contract documents provided for the possibility of adjusting certain conditions, even material ones, after the contract had been awarded and fixed the detailed rules for the application of that possibility.