66Since it follows from the foregoing, first, that the Council was required to communicate Regulation No 363/2013 directly to the applicant and, second, that if such communication was not validly made, the period with which the applicant was required to comply in order to challenge that act before the Court never began to run, it must be established whether the Council fulfilled that obligation.