Judgment of the Court (Grand Chamber)15 January 2013note(Article 267 TFEU — Annulment of a judicial decision — Referral back to the court concerned — Obligation to comply with the annulment decision — Reference for a preliminary ruling — Whether possible — Environment — Aarhus Convention — Directive 85/337/EEC — Directive 96/61/EC — Public participation in the decision-making process — Construction of a landfill site — Application for a permit — Trade secrets — Non-communication of a document to the public — Effect on the validity of the decision authorising the landfill site — Rectification — Assessment of the environmental impact of the project — Final opinion prior to accession of the Member State to the European Union — Application in time of Directive 85/337 — Effective legal remedy — Interim measures — Suspension of implementation — Annulment of the contested decision — Right to property — Interference)In Case C-416/10,REQUEST for a preliminary ruling under Article 267 TFEU from the Najvyšší súd Slovenskej republiky (Slovakia), made by decision of 17 August 2010, received at the Court on 23 August 2010, in the proceedingsJozef Križan,Katarína Aksamitová,Gabriela Kokošková,Jozef Kokoška,Martina Strezenická,Jozef Strezenický,Peter Šidlo,Lenka Šidlová,Drahoslava Šidlová,Milan Šimovič,Elena Šimovičová,Stanislav Aksamit,Tomáš Pitoňák,Petra Pitoňáková,Mária Križanová,Vladimír Mizerák,Ľubomír Pevný,Darina Brunovská,Mária Fišerová,Lenka Fišerová,Peter Zvolenský,Katarína Zvolenská,Kamila Mizeráková,Anna Konfráterová,Milan Konfráter,Michaela Konfráterová,Tomáš Pavlovič,Jozef Krivošík,Ema Krivošíková,Eva Pavlovičová,Jaroslav Pavlovič,Pavol Šipoš,Martina Šipošová,Jozefína Šipošová,Zuzana Šipošová,Ivan Čaputa,Zuzana Čaputová,Štefan Strapák,Katarína Strapáková,František Slezák,Agnesa Slezáková,Vincent Zimka,Elena Zimková,Marián Šipoš,Mesto PezinokvSlovenská inšpekcia životného prostredia,Ekologická skládka as,THE COURT (Grand Chamber),composed of V. Skouris, President, K. Lenaerts, Vice-President, A. Tizzano, M. Ilešič, L. Bay Larsen (Rapporteur), J. Malenovský, Presidents of Chambers, A. Borg Barthet, J.-C. Bonichot, C. Toader, J.-J. Kasel and M. Safjan, Judges,Advocate General: J. Kokott,Registrar: C. Strömholm, Administrator,having regard to the written procedure and further to the hearing on 17 January 2012,after considering the observations submitted on behalf of:— Jozef Križan, Katarína Aksamitová, Gabriela Kokošková, Jozef Kokoška, Martina Strezenická, Jozef Strezenický, Peter Šidlo, Lenka Šidlová, Drahoslava Šidlová, Milano Šimovič, Elena Šimovičová, Stanislav Aksamit, Tomáš Pitoňák, Petra Pitoňáková, Mária Križanová, Vladimír Mizerák, Ľubomír Pevný, Darina Brunovská, Mária Fišerová, Lenka Fišerová, Peter Zvolenský, Katarína Zvolenská, Kamila Mizeráková, Anna Konfráterová, Milano Konfráter, Michaela Konfráterová, Tomáš Pavlovič, Jozef Krivošík, Ema Krivošíková, Eva Pavlovičová, Jaroslav Pavlovič, Pavol Šipoš, Martina Šipošová, Jozefína Šipošová, Zuzana Šipošová, Ivan Čaputa, Zuzana Čaputová, Štefan Strapák, Katarína Strapáková, František Slezák, Agnesa Slezáková, Vincent Zimka, Elena Zimková, Marián Šipoš, by T. Kamenec and Z. Čaputová, advokáti,— Mesto Pezinok, by J. Ondruš and K. Siváková, advokáti,— Slovenská inšpekcia životného prostredia, by L. Fogaš, advokát,— Ekologická skládka as, by P. Kováč, advokát,— the Slovak Government, by B. Ricziová, acting as Agent,— the Czech Government, by M. Smolek and. D. Hadroušek, acting as Agents,— the French Government, by S. Menez, acting as Agent,— the Austrian Government, by C. Pesendorfer, acting as Agent,— the European Commission, by P. Oliver and A. Tokár, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 19 April 2012,gives the following
Judgment
Legal context
International law
European Union law
Directive 85/337
Directive 96/61
Directive 2003/4/EC
Slovak law
Procedural rules
The provisions on environmental impact assessments, urban planning rules and integrated permits
–Law No 24/2006 Z.z.
Law No 50/1976 Zb.
–Law No 245/2003 Z.z.
The dispute in the main proceedings and the questions referred for a preliminary ruling
The administrative procedure
The judicial proceedings
Consideration of the questions referred
Admissibility
The first question
The second question
The third question
The fourth question
The fifth question
Costs
Operative part