Judgment of the Court (First Chamber)11 November 2010noteIn Case C-543/08,ACTION under Article 226 EC for failure to fulfil obligations, brought on 4 December 2008,European Commission, represented by G. Braun, P. Guerra e Andrade and M. Teles Romão, acting as Agents, with an address for service in Luxembourg,vPortuguese Republic, represented by L. Inez Fernandes, assisted by C. Botelho Moniz and P. Gouveia e Melo, advogados,THE COURT (First Chamber),composed of A. Tizzano, President of the Chamber, A. Borg Barthet, M. Ilešič, M. Safjan and M. Berger (Rapporteur), Judges,Advocate General: P. Cruz Villalón,Registrar: M. Ferreira, Principal Administrator,having regard to the written procedure and further to the hearing on 22 April 2010,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
National legislation
EDP’s articles of association
Background to the case and pre-litigation procedure
Admissibility of the action
Arguments of the parties
Findings of the Court
Substance
Whether there are restrictions
Arguments of the parties
Findings of the Court
—The applicability of Articles 56 EC and 43 EC
—The failure to fulfil obligations under Article 56 EC
Whether the restrictions are justified
Arguments of the parties
Findings of the Court
The failure to fulfil obligations under Article 43 EC
Costs
Operative part