49It should be borne in mind in this respect that, under Article 14(3) of Regulation No 659/1999, the application of national procedures is subject to the condition that those procedures allow the immediate and effective execution of the Commission's decision, a condition which reflects the requirements of the principle of effectiveness laid down previously by case-law (see Case 94/87 Commission v Germany [1989] ECR I-175, paragraph 12; Case C-24/95 Alcan Deutschland [1997] ECR I-1591, paragraph 24, and Commission v Germany, cited above, paragraphs 32 to 34).