98It must be borne in mind that economic operators must bear the economic risks inherent in their activities, regard being had to the circumstances of each particular case. As regards a tendering procedure, those economic risks include, in particular, the costs relating to preparation of the tender. The expenses thus incurred therefore remain the responsibility of the undertaking which chose to take part in the procedure, since the opportunity to compete for a contract does not involve any certainty as to the outcome of the procedure. In accordance with that principle, Article 24 of the General Regulations for Tenders and the Award of Service Contracts financed from Phare/Tacis Funds provides that in the event of closure or annulment of a tendering procedure, the tenderers are not entitled to compensation. It follows that the charges and expenses incurred by a tenderer in connection with his participation in a tendering procedure cannot in principle constitute damage which is capable of being remedied by an award of damages. However, the provision in question cannot, without potentially undermining the principles of legal certainty and of protection of legitimate expectations, apply in cases where an infringement of Community law in the conduct of the tendering procedure has affected a tenderer's chances of being awarded the contract (Case T-203/96 Embassy Limousines & Services v Parliament [1998] ECR II-4239, paragraphs 75 and 97, and Case T-13/96 TEAM v Commission [1998] ECR II-4073, paragraphs 70 to 72).
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.