Judgment of the Court (Second Chamber)20 January 2005noteIn Case C-296/03,REFERENCE for a preliminary ruling under Article 234 EC by the Conseil d'État (Belgium) by decision of 27 June 2003, received at the Court on 8 July 2003, in the proceedingsGlaxosmithkline SAvÉtat Belge,THE COURT (Second Chamber),composed of C.W.A. Timmermans, President of the Chamber, R. Silva de Lapuerta (Rapporteur), C. Gulmann, P. Kūris and G. Arestis, Judges,Advocate General: A. Tizzano,Registrar: M. Múgica Arzamendi, Principal Administrator,having regard to the written procedure and further to the hearing on 14 July 2004,after considering the observations submitted on behalf of:— Glaxosmithkline SA, by S. Callens and S. Brillon, avocats,— the Belgian Government, by E. Dominkovits, acting as Agent, and by L. Levi and L. Depré, avocats,— the Danish Government, by J. Molde, acting as Agent,— the Netherlands Government, by H.G. Sevenster, acting as Agent,— the Finnish Government, by T. Pynnä and A. Guimaraes-Purokoski, acting as Agents,— the Norwegian Government, by A. Enersen and F. Platou Amble, acting as Agents,— the Commission of the European Communities, by B. Stromsky, acting as Agent,after hearing the Opinion of the Advocate General at the sitting on 30 September 2004,gives the following
Judgment
Legal framework
Community rules
National rules
Main proceedings and question referred to the Court
The question referred to the Court
Admissibility
Substance
The indicative or mandatory nature of the time-limit laid down in the first subparagraph of Article 6(1) of the Directive
The consequences of exceeding the time-limit where a previous decision adopted in good time has been annulled
Costs
Operative part