Judgment of the Court of First Instance (Third Chamber)3 April 2003noteIn Case T-114/02,BaByliss SA, established in Montrouge (France), represented by J.-P. Günther, lawyer,De'Longhi SpA, established in Trévise (Italy), represented by M. Merola, D. Domenicucci and I. van Schendel, lawyers,vCommission of the European Communities, represented by V. Superti, K. Wiedner and F. Lelièvre, acting as Agents, with an address for service in Luxembourg,SEB SA, established in Écully (France), represented by D. Voillemot and S. Hautbourg, lawyers,THE COURT OF FIRST INSTANCE OF THE EUROPEAN COMMUNITIES (Third Chamber),composed of: K. Lenaerts, President, J. Azizi and M. Jaeger, Judges,Registrar: J. Palacio González, Principal Administrator,having regard to the written procedure and further to the hearing on 9 October 2002,gives the following
Judgment
Relevant legislation
Facts
I —The undertakings concerned
II —National proceedings
III —Procedure before the Commission
The contested decision
I —The relevant product markets
II —The relevant geographical markets
III —Importance of the trade marks
IV —Competition analysis
V —Commitments of the parties to the concentration
VI —State aid
Procedure and forms of order sought by the parties
Admissibility
I —Arguments of the parties
II —Findings of the Court
The substance of the case
I —First plea: breach of essential procedural requirements in that the Commission accepted the belated submission of commitments by SEB
Arguments of the parties
Findings of the Court
II —Second plea: the Commission erred in law in authorising the concentration without opening phase II
Arguments of the parties
Findings of the Court
III —Third plea: manifest error of assessment in that the commitments were insufficient to overcome the competition problems
First limb: a commitment to grant a trade mark licence is not by nature capable of remedying the competition problems caused by the concentration
A —Arguments of the parties
B —Findings of the Court
Second limb: manifest error of assessment by the Commission in accepting commitments of insufficient duration
A —Arguments of the parties
B —Findings of the Court
Third limb: the commitment to provide supplies on the German market and the conditions attached to the option for all licensees to obtain supplies will have the effect of strengthening the position of SEB-Moulinex
A —Arguments of the parties
B —Findings of the Court
Fourth limb: the fact that the Commission agreed that the Moulinex trade mark could be used by different undertakings in different States of the European Union may give rise to collusion between SEB-Moulinex and the licensee or licensees
A —Arguments of the parties
B —Findings of the Court
Fifth limb: the Commission authorised the concentration without commitments relating to markets with serious competition problems
A —Arguments of the parties
B —Findings of the Court
1.Admissibility
2.Substance
(a)The four stages of the examination
—The dominance threshold of 40%
—No significant overlap
—The position of the merged entity in relation to competitors
—The range effect
(b)The countries not covered by the commitments
—Norway
—Spain
—Finland
—Italy
—United Kingdom and Ireland
(c)Conclusion
The plea that the commitments bring about a sharing of the market for the Moulinex trade mark
A —Arguments of the parties
B —Findings of the Court
IV —Fourth plea in law: the Commission erred in law in failing to consider whether the nominal price paid by SEB for the acquisition of Moulinex and the financial aid provided by the French State were not such as to strengthen SEB's position in the markets concerned, to the detriment of competitors
Arguments of the parties
Findings of the Court
Costs