law://eu/cjeu/1980/c-171-80/hd_1_1_3@2026-11-29In its application the Commission submits that the binding nature of directives, as to the result to be achieved, implies that Member States are bound to observe the periods laid down by them.The Court declared in the judgment of 26 February 1976 in Case 52/75 Commission v Italian Republic [1976] ECR 277 that:“The correct application of a directive is particularly important since the implementing measures are left to the discretion of the Member States and would be ineffective if the desired aims are not achieved within the prescribed time-limits. Although the provisions of a directive are no less binding on the Member States to which they are addressed than the provisions of any other rule of Community law, such an effect attaches a fortiori to the provisions relating to the periods allowed for implementing the measures prescribed, in particular since the existence of differences in the rules applied in the Member States after these periods have expired might result in discrimination.”Furthermore, in the judgment of 11 April 1978 in Case 100/77 Commission v Italian Republic [1978] ECR 879 and in the judgment of 22 February 1979 in Case 163/78 Commission v Italian Republic [1979] ECR 771 the Court made it plain that a Member State “cannot rely upon domestic difficulties or provisions of its national legal system, even its constitutional system, for the purpose of justifying a failure to comply with obligations and periods resulting from Community directives”.In its defence the Italian Government stresses that in order to accelerate the adaptation of its legal system in accordance with the Community directives it recently took the step of requesting Parliament to delegate the legislative powers provided for by Article 76 of the Constitution in order to facilitate by means of decrees the promulgation of rules, having legal force and status, required to implement a number of Community directives. The delegation was approved by the Senate on 16 July 1980 when it passed a special draft Law which has been sent to the Chamber of Deputies for scrutiny.The Italian Government observes that the relatively long duration of the legislative process of delegating authority is due to the high number of directives involved in that process and thus to the broad scope of the powers to be delegated; but the time lost will be more than made up by the impetus given to such comprehensive action for incorporating Community principles on standardization.The priority given to the entire procedure evinces the Italian Government's firm intention to meet its Community commitments on directives and is a guarantee that there can be no doubt that the directives on the marketing and the use of dangerous substances and preparations will be incorporated into the Italian legal system.The Commission, represented by Alberto Prozzillo, acting as Agent, and the Italian Republic, represented by Ivo Maria Braguglia, Avvocato dello Stato, acting as Agent, presented oral argument at the sitting on 13 January 1981.The Advocate General delivered his opinion at the sitting on 28 January 1981.
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.