In Case 139/73Reference to the Court under Article 177 of the EEC Treaty by the Hessischer Verwaltungsgerichtshof for a preliminary ruling in the action pending before that court betweenEINFUHR- UND VORRATSSTELLE FÜR GETREIDE UND FUTTERMITTEL, Frankfurtam-Main, Adickesallee 1,andEUGEN MUNCH, Getreidemühle, Horgen, Unterbergstraße 38,THE COURTcomposed of: R. Lecourt, President, A. M. Donner and M. Sørensen, Presidents of Chambers, R. Monaco, J. Mertens de Wilmars (Rapporteur), P. Pescatore, H. Kutscher, C. Ó Dálaigh, A. J. Mackenzie Stuart, Judges,Advocate-General: G. ReischlRegistrar: A. Van Houttegives the following
Judgment
Issues of fact and of law
The facts of the case, the purpose of the reference and the observations submitted under Article 20 of the Statute of the Court of Justice may be summarized as follows:
I —Facts and procedure
By a communication dated 7 August 1971, despatched on Monday, 9 August 1971, Firma Munch, plaintiff in the action at first instance, respondent before the national court, claimed the grant of a carry-over payment of DM 764.28 for 33100 kg of common wheat, held in stock at the end of the 1970/71 marketing season. This claim was rejected by the ‘Einfuhr- und Vorratsstelle’, the defendant in the action at first instance and appellant before the national court, on the grounds that according to Article 3 of Regulation No 1196/71 of the Commission of 8 June 1971 it should have been despatched on 7 August 1971 at the latest.Firma Münch filed a suit in the Frankfurt Verwaltungsgericht claiming the grant of the carry-over payment previously requested.The claim was upheld at first instance; the national court was of the opinion that pursuant to Article 3 (4), first paragraph, of Regulation No 1182/71 of the Council of 3 June 1971, the period did not expire until 9 August 1971, 7 August 1971 being a Saturday.The defendant in the main action appealed against this judgment to the Hessischer Verwaltungsgerichtshof on the basis of Article 3 (4), second paragraph, of Regulation No 1182/71. By order of that court of 11 May 1973 the following questions were referred to the Court of Justice:1. Must the requirement in Article 3 — last indentation — of EEC Regulation No 1196/71 of the Commission dated 8 June 1971 (OJ L 125, 9. 6. 1971, p. 12) be interpreted as fixing a period within the meaning of Article 3 of Regulation (EEC, Euratom) No 1182/71 of the Council dated 3 June 1971 (OJ L 124, 8. 6. 1971, p. 1)?2. If it does fix such a period, is the definition in Article 3 (4), first paragraph, of Regulation (EEC, Euratom) No 1182/71 applicable, or does Article 3 (4), second paragraph, of the last-mentioned Regulation apply?3. If (1) is answered in the negative, must the requirement in Article 3 — last indentation — of EEC Regulation No 1196/71 be interpreted as fixing a date within the meaning of Article 5 of Regulation (EEC, Euratom) No 1182/71?This order was registered at the Court on 4 June 1973.Upon hearing the report of the Judge-Rapporteur and the opinion of the Advocate-General, the Court decided to open the oral procedure without any preparatory inquiry. Firma Munch and the Commission submitted written observations.The respondent in the main action, represented by Me Preuss, Rechtsanwalt, of the Mannheim Bar, and the Commission, represented by Mr Wägenbauer, as agent, made oral observations at the hearing on 23 October 1973.The Advocate-General delivered his opinion at the hearing on 7 November 1973.
II —Observations submitted under Article 20 of the Statute of the Court of Justice
A —Observations submitted by the Commission
After recalling that according to the case law of the Court (Case 32/72, Wasaknäcke, Rec. 1972, p. 1186 and Case 52/72, Walzenmühle Magstadt, Rec. 1972, p. 1272), the period fixed pursuant to Article 9 of Regulation No 120/67 EEC for the despatch of claims for carry-over payments is absolute, the Commission raises the question whether Regulation No 1182/72 of the Council, determining the rules applicable to periods, dates and time limits, applies to Regulation No 1196/72. Article 1 of Regulation No 1182/71 in fact allows derogations from the rules it lays down and it is conceivable that Regulation No 1196/71 involves such a derogation.If Regulation No 1182/71 is taken to apply in this case then it must be conceded that Article 3 — last indentation — of Regulation No 1196/71 does not contain a ‘period’ within the meaning of Articles 2 and 3 of Regulation No 1182/71 but rather a date or time limit within the meaning of Article 5 of the same Regulation. The concept of a ‘period’ (‘délai’) in fact presupposes the indication of a defined amount of time, which is not the case here.The first question should accordingly be answered in the negative; this would make it unnecessary to answer the second question, while the third question should be answered in the affirmative. Article 3 (4) and (5), allowing the extension of ‘periods’, does not therefore apply.
B —Observations submitted by Firma Munch
The respondent shares the opinion of the Frankfurt Verwaltungsgericht that Article 3 of Regulation No 1196/71 of the Commission provides for a period within the meaning of Articles 2 and 3 of Regulation No 1182/71 of the Council.The reference to the Court of Justice for a preliminary ruling was occasioned solely by the fact that it had not clearly been established whether periods, the beginning and end of which were expressed as dates, were to be understood as periods within the meaning of Regulation No 1182/71. It appears, both from the preamble to Regulation No 1182/71 and from the distinction drawn between the calculation of the period and its establishment, that the authors of the Regulation also had in mind periods which are expressed in terms of dates for beginning and ending, and which can therefore be applied without any further calculation.If this is a period within the meaning of Article 3 of Regulation No 1182/71, the first and not the second paragraph of Article 3 (4) of that Regulation should be applied, so that the period should be extended to the next working day, that it, 9 August 1971.Accordingly it is unnecessary to answer the third question, since the case covered by Article 5 of Regulation No 1182/71, namely that where an action is to be effected at a specified moment, at a specified date or within a given number of days following the moment when an event occurs or another action takes place, is not the present case. Moreover Article 5 is only concerned with specific acts, that is, in all probability, acts of the public bodies and institutions of the Member States with regard to the Community, since only those institutions can perform acts of a legal nature.
Grounds of judgment
Costs
Operative part